WHS Construction Information

If you have a question to be answered about the construction phase of the project please check out the 

Frequently Asked Questions


Wells High School Building Project:

Look Ahead for the Week of 04/27/15

Click on the image to see day-to-day items 
Week Ahead for April 27, 2015

*Projects subject to change based on conditions and other factors



Project Timeline

Phase 1:

-       New addition to start construction in August 2014 and open in January 2016.

Milestones for first seven months:

  • Foundation Work and Underground Electrical/Mechanical   9/14 - 11/14
  • Structural Steel  12/14 - 2/15
  • Roofing and Framing  1/15 - 3/15
  • Windows  2/15 - 4/15
  • Curtain Wall  2/15 - 3/15

*Time spans subject to change based on contractor and other factors

-       Competition Gym to start and be completed for use in the Summer of 2015 

 

Phase 2:

-       Existing classroom wing to be demolished after January 2016.

-       Auditorium to be renovated between January 2016 and end of August 2016

-       PE Gym and walking track to be renovated between January 2016 and end of August 2016

 

Phase 3:

-       Kitchen to be renovated in the Summer of 2016.

Monthly Update From the Field

Report from the field 03.15


Archives



Project Floorplan
WHS Floor Plan


Project Slideshow


WHS Construction Phase


WHS Groundbreaking





Project Timeline